Bradfords Warehouse, Sherborne

This project involved the design and construction of a new warehouse for Bradfords Building Supplies in Sherborne.

The new builder's merchant unit is split into trade counter areas, warehousing and support office areas, with approximately 2,300m² of yard/display/storage and car parking areas.

This contract was delivered 2 months ahead of programme to a delighted client! The original completion date was scheduled for 9th September, however practical completion was achieved on 16th July enabling the client to start using their brand new facility well ahead of the grand opening on 26th September 2019.

Category: Retail

Overview

Location Sherborne, Dorset
Client Bradfords Building Supplies Ltd (Yeovil)
Architect Boon Brown Architects
Contract Value £2.57m
Contract Period 46 weeks (delivered in 37)

More Projects

See more Retail projects by clicking the link(s) below:


Location


Contact

Tel: 01305 267938 (Head Office)

Tel: 02380 171671 (Hampshire Office)

Email: ac@achesonconstruction.com

Share

Related News